![]() ![]() ![]() Interests: Project Management and MS PROJECT After Hide / Show the same Column I’ll get: I changed the Status field from NA to, and I get: If it does NOT refresh repeat this steps: You can sort on it, filter on it etc.īut, be aware that in some situations it will not be change according to changing status Date. ![]() Now, Task 1, and Task 2 are Completed, Task 3 is Late, and Task 4 is Future Task. No I’ll make Task 1, and Task 2 completed: I’m going to change Status date from NA to Sunday, :Īs you can see Task 1, Task 2, and Task 3 are late according to Status date. Today I’ll show you how Status field works in MS PROJECT 2013.Īs usual I am going to Create some Tasks:Īs you can see Task 1 is On Schedule, because today is Mon.